Portland International Airport

Modular Delivery at Airport Scale

Project Facts

Location Portland, Oregon
Owner Port of Portland
Size 380,000 SF
Cost $950 million
Status Completed 2025
Certifications Pursuing LEED Gold

Overview

The Portland International Airport Main Terminal Redevelopment introduced a nine-acre, timber-framed roof while maintaining uninterrupted airport operations. Walter P Moore provided construction engineering for modular fabrication transport, and installation of the roof system. 

Challenges

Active Terminal Below

Construction occurred above an operating airport terminal, limiting allowable shutdowns and increasing safety and operational constraints.

Large Curved Geometry

The expansive, curved roof geometry introduced complexity in fabrication, transport, and placement of long-span structural elements.

Timber-Steel Hybrid

The roof combined sustainably sourced timber with steel framing, requiring careful stability control during temporary and permanent conditions.

Restricted Site Access

Tight site conditions required efficient movement and positioning of oversized roof components within a constrained footprint.

Modular roof cassettes assembled off-site to reduce construction impacts within the live terminal.

Prefabricated roof cassettes prepared for transport and installation using a modular construction approach.

Modular roof cassettes assembled off-site to reduce construction impacts within the live terminal.

Prefabricated roof cassettes prepared for transport and installation using a modular construction approach.

1 / 1

Solutions

Modular Roof Cassettes

The roof was segmented into prefabricated cassettes, each approximately 80 feet by 170 feet, allowing work to proceed away from the terminal.

Temporary Works Design

Engineers developed adjustable temporary shoring and stability plans to support timber and steel components during prefabrication and erection.

SPMT Transportation

Self-propelled modular transporters moved completed cassettes from the laydown yard to the terminal, minimizing on-site handling.

Controlled Launch Sequence

Engineered launch procedures used jacking, temporary locking, and sequencing to safely position each cassette onto the supporting Y-columns.

1 / 1

Results

Reduced Overhead Work

Modular installation eliminated months of heavy construction above the terminal, reducing risk to passengers and staff.

Improved Site Safety

Off-site prefabrication and controlled installation sequences significantly reduced worker exposure in active terminal areas.

Accelerated Installation

Prefabrication enabled faster roof installation once cassettes were delivered to the terminal footprint.

Integrated Systems

Each cassette arrived with structural, mechanical, and electrical components integrated, streamlining final connections and finishes.