Houston Methodist Hospital Centennial Tower

Engineering Above Active Operations

Project Facts

Location Houston, Texas
Owner Houston Methodist
Size 1,200,000 SF
Status Under Construction
Capacity 400 beds

Overview

Houston Methodist Hospital Centennial Tower is a 26-story patient care facility that expands and connects the hospital’s Texas Medical Center campus. Walter P Moore provided structural engineering for the tower and construction engineering for the multistory pedestrian bridge connecting the new facility to the existing Walter Tower. The design and erection strategies had to accommodate active roadways, emergency access, critical underground utilities and limited crane capacity within a highly constrained hospital campus.

Challenges

Column-Free Building Corner

The tower’s northwest corner required more than 50 feet of cantilever to preserve ambulance parking, vehicular circulation and headroom while avoiding an existing underground utility that had to remain operational.

Constrained Bridge Site

The pedestrian bridge spans active roadways and connects to operational hospital facilities, leaving limited space for cranes, staging and temporary support.

Limited Existing Capacity

The bridge had to connect to Walter Tower without transferring significant additional loads to the existing structure. 

Complex Temporary Loading

The elevated transfer girder supports columns above while suspending columns and floors below, creating temporary loading conditions that changed as construction progressed.

Dense Structural Detailing

The transfer girder required substantial post-tensioning and reinforcing within a 27-foot-deep system while accommodating cladding setbacks, construction access and connections to adjacent floor plates.

Solutions

Elevated Transfer System

Engineers located a 53-foot-long cantilevering transfer girder within a mechanical level, using its taller story height to preserve clearance above the ambulance drive. A 68-foot backspan helped balance the cantilevered load and reduce uplift.

Post-Tensioned Girder Design

The 8,000-psi concrete girder uses approximately 300 post-tensioning tendons to control deflection and reduce reinforcing congestion. Strut-and-tie modeling addressed deep-beam behavior and critical discontinuity regions.

Incremental Bridge Erection

The bridge was divided into smaller assemblies compatible with the available tower cranes. The erection strategy allowed crews to build the bridge incrementally and cantilever it outward from Centennial Tower without conventional shoring below.

Temporary Stability Design

Assembly weight estimates, crane capacity evaluations, rigging concepts and temporary stability provisions informed how each bridge segment could be lifted, secured and connected safely during erection. 

Staged Load Transfer

Staged construction analysis predicted tower behavior as loads shifted from temporary supports to the permanent transfer girder. Temporary steel supports and sand jacks facilitated controlled load transfer and support removal. 

1 / 1

Results

Protected Campus Operations

The structural configuration maintained ambulance access, vehicular circulation and operation of the existing underground utility while supporting the tower above.

More Buildable Reinforcing

Increasing tendon diameter from 0.5 inch to 0.6 inch reduced the required tendon count by approximately 30%, helping manage congestion at anchorages and within the reinforcing cage.

Verified Structural Behavior

Field monitoring showed that observed transfer-system deflections tracked predicted behavior during early construction stages and remained below predictions as work progressed.

Reduced Existing Loads

The completed bridge transfers most gravity and construction loads to Centennial Tower, limiting additional demand on Walter Tower.

Shoring-Free Bridge Installation

Segmenting the bridge for tower-crane erection provided a feasible installation strategy where active traffic, underground infrastructure and limited access prevented conventional temporary shoring.

Perspectives